https://newsletter-en.creamermedia.com
Banco De Fomento Angola|DRA|FEECO International|Grupo Arliz|Minbos Resources|SRK|Angola|South Africa|Cabinda Phosphate Project|Cácata Mine|Fertiliser|Phosphate|IFDC|Industrial Development|Cabinda
|||||
banco-de-fomento-angola|dra|feeco-international|grupo-arliz|minbos-resources|srk|angola|south-africa|cabinda-phosphate-project|ccata-mine|fertiliser|phosphate|ifdc|industrial-development|cabinda

Cabinda phosphate project, Angola – update

Location map of the Cabinda phosphate project

Photo by Minbos Resources

26th June 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Cabinda phosphate project.

Location
Cabinda province, Angola. 

The Cabinda phosphate fertiliser plant is being developed in the Subantando commercial precinct, about 36 km from Cácata and 16 km from Cabinda port.

Project Owner/s
Minbos Resources, through its subsidiary Phobos and the Angolan project companies Soul Rock Lda and Minbos Resources Lda. 

Project Description
The integrated phosphate mine and fertiliser project comprises the Cácata openpit phosphate mine and the Cabinda phosphate fertiliser plant at Subantando. The plant was originally planned for the Futila Industrial Zone. Minbos subsequently relocated it to Subantando. 

The Cácata deposit has proven and probable ore reserves of 4.72-million tonnes grading 30.1% phosphorous pentoxide. Mining is planned using conventional openpit truck-and-shovel methods.

The 2022 definitive feasibility study (DFS) envisages staged production from an initial 187 500 t/y plant train, with expansion to two trains. Average fertiliser production over the estimated 20-year project life is forecast at about 236 000 t/y.

Minbos is also pursuing an accelerated-start strategy under which uncrushed phosphate rock could be dewatered at the mine, screened and stored at Subantando, and sold before the full beneficiation and granulation circuit is commissioned. Full-scale beneficiation and granulation remain part of the longer-term development strategy.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The October 2022 DFS estimates an after-tax net present value, at a 10% discount rate, of $203.2-million and an internal rate of return of 39%, with a payback period of 4.8 years. 

Capital Expenditure
The October 2022 DFS estimated capital expenditure at $48.5-million. This estimate predates the relocation and redesign of the plant and the accelerated-start strategy, which Minbos has said could defer about $20-million of initial capital expenditure. The Phase 2 construction contract, the scope of which covers activities until dry commissioning is valued at $13.8-million.

Planned Start/End Date
Phase 1 civil construction has been completed. Phase 2 construction will advance the plant through structural, mechanical, electrical and instrumentation installation to dry commissioning. 

Latest Developments
On June 22, 2026, Minbos signed a $13.8-million Phase 2 construction contract with Grupo Arliz for all the remaining works required to advance the fertiliser plant to dry commissioning. The scope includes structural steel, mechanical installation, electrical and instrumentation works, and process-control systems.

Grupo Arliz also completed Phase 1 comprising the project platform, roads, drainage, slabs and foundations. The plant and equipment, which were designed by FEECO International and shipped to Angola in 2023, are in Cabinda and ready for assembly.

Minbos received the first $4.8-million drawdown under its $16-million Industrial Development Corporation of South Africa (IDC) facility in June 2026 and ordered long-lead items. 

A $5.48-million Banco de Fomento Angola term sheet was signed in May 2026. 

Minbos has said that the IDC facility and proposed BFA funding are sufficient to complete construction of the fertiliser plant.

Key Contracts, Suppliers and Consultants
Grupo Arliz (Phase 1 civil works and Phase 2 construction through to dry commissioning); FEECO International (plant design and major equipment supply); DRA (process plant design and costing); IFDC (fertiliser trials, granulation and beneficiation pilot testing, process design inputs and marketing studies); Moisture Reduction Systems (stockpile dewatering technology for the accelerated-start strategy); Mintek (material characterisation); SRK (mineral resource statement); Orelogy/Majesso (pit optimisation, mine design, scheduling, reserve statement and contract mining cost estimates); GRD Engenharia (plant-site geotechnical studies); HCV Africa (environmental baseline and social studies and environmental and social-impact assessment); and Grupo Simples (environmental-impact study and waste management plan).

Contact Details for Project Information
Minbos Resources, tel +61 8 6219 7171 or email info@minbos.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ECG Engineering
ECG Engineering

ECG provides specialised electrical engineering services to the Mining, Utilities, Materials Handling and Industrial industries, with extensive and...

VISIT SHOWROOM 
Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 26 June 2026
Magazine round up | 26 June 2026
26th June 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 0.743s - 146pq - 2rq
Subscribe Now