Steenkampskraal monazite mine, South Africa – update

Shaft at the Steenkampskraal project

Photo by Steenkampskraal Holdings

26th June 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Steenkampskraal monazite mine (SMM).

Location
Western Cape, South Africa.

Project Owner/s
Steenkampskraal Holdings (SHL). 

Project Description
The Steenkampskraal mine is an existing mine that produced and exported a monazite concentrate during the 1950s and 1960s.

The mine is considered one of the highest-grade rare earths and thorium mines in the world. The mine deposit is rich in neodymium/praseodymium, dysprosium, terbium and other rare-earth minerals. The primary elements at the mine are neodymium – 56.59%, dysprosium – 14.19%, praseodymium – 12.43%, terbium – 9.62%, gadolinium – 2.12% and cerium – 1.95%.

The mine’s design has been developed for optimum use of the existing underground infrastructure and is based on conventional stoping techniques, tramming the ore to the bottom of the incline shaft and hoisting it up the incline shaft.

Steenkampskraal has been structured as a series of interlinked phases, every one designed to capture additional value by moving further downstream in the rare earth supply chain.

Phase 1 will involve the mobilisation of the mining and processing plant and equipment to the site, refurbishment of the decline and shaft area, and the re-equipping of the headgear and infrastructure.

Material and loose ore from underground will be reclaimed, followed by the construction of the monazite – a brown crystalline mineral comprising a phosphate of cerium, lanthanum, other rare-earth elements (REE) and thorium – concentration plant and start of underground mining. A minimum of 5 000 t/y of monazite concentrate will be produced in the first phase.

Phase 2 will involve increased mining volumes and monazite concentrate production and all metallurgical testwork, design and planning for the construction and commissioning of a monazite cracking plant. This will produce mixed  rare-earth carbonate (MREC) and thorium. The design and planning of a rare earths separation plant will also be undertaken during this phase.

The construction and commissioning of the separation plant will be completed to produce mixed rare-earth oxides (REO) in Phase 3. 

Potential Job Creation
About 200 jobs are expected to be created.

Net Present Value/Internal Rate of Return
In Phase 1, the value of monazite concentrate will generate a net present value (NPV) of more than $200-million. In Phase 2, the value of MREC, excluding thorium, will be $5 200/t, with an expected NPV of more than $300-million. In Phase 3, the expected revenue for separated rare earths, based on an average price of $37 000/t, will generate an NPV of more than $620-million. 

Capital Expenditure
The project will require low initial capital.
 
Planned Start/End Date
From January 2026 to December 2026, the cracking plant will be commissioned, with the initial production of MREC and thorium. 

From January 2027, the steady-state production of monazite concentrate to the cracking plant will be undertaken, with the production of MREC and thorium, and plans to produce individual REOs.

Latest Developments
SMM and South Africa’s national mineral research organisation Mintek have announced the successful production of high-purity mixed rare earth products at Mintek’s laboratory facilities.

This forms the foundation of the start of commercial production of rare earth products in South Africa before the end of 2026, with longer-term expansion to include REE and thorium beneficiation, as well as medical isotope production.

The milestone, achieved through a long-standing collaboration between the two organisations, positions South Africa as the first African country to successfully produce rare earth products through a partnership between a mining company and a national research institution.

Construction of the processing plant is progressing well, with concentrate production expected to start later this year and first shipments expected before the end of this year.

The mine continues to engage with several strategic investors currently conducting due diligence regarding potential participation in the project.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
SHL, tel +27 21 852 4998, fax +27 086 619 7330 or email info@steenkampskraal.com


 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Columbus Stainless
Columbus Stainless

Columbus Stainless, based in Middelburg, Mpumalanga, is Africa’s only producer of stainless steel flat products. In addition, Columbus is the only...

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 26 June 2026
Magazine round up | 26 June 2026
26th June 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.048 1.564s - 132pq - 2rq
Subscribe Now