Alaska liquefied natural gas project, US – update

Image of Alaska LNG facility

Photo by Glenfarne Group

23rd October 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Alaska liquefied natural gas (LNG) project.

Location
Alaska, in the US.

Project Owner/s
Energy infrastructure developer, owner and operator Glenfarne Group, through Glenfarne Alaska LNG, is the developer and 75% owner. The state of Alaska owns the remaining 25% through Alaska Gasline Development Corporation (AGDC).

Project Description
The project is being developed in two financially independent phases. 

Phase 1 comprises a 1 189 km, 42-inch-diameter pipeline supplying North Slope natural gas to domestic consumers. 

Phase 2 adds LNG liquefaction and related infrastructure at Nikiski, extending the mainline to about 1 299 km and allowing for exports of 20-million tonnes a year. 

The Nikiski LNG facility is planned to include three trains, two 240 000 m³ storage tanks, terminal and marine facilities, and two loading berths accommodating carriers of up to 217 000 m³.

The full mainline has a stated capacity of 3.3-billion cubic feet a day. The project includes a North Slope gas treatment plant. 

Potential Job Creation
The project is expected to create 12 000 construction jobs and up to 1 000 long-term operations jobs.

Capital Expenditure
The AGDC estimates that the cost of the facilities will be between $40-billion and $45-billion.

Planned Start/End Date
Glenfarne announced on January 22, 2026, that mechanical completion of the Phase 1 pipeline was targeted for 2028 and first gas delivery for 2029. 

Latest Developments
On September 30, 2026, Glenfarne welcomed an announced South Korean investment of more than $50-billion in Alaska LNG. The company said it would work with the US and Korean governments to finalise the investment structure and complete the remaining steps towards a final investment decision (FID). 

Commercial agreements represented 13-million tonnes a year of the 16-million tonnes a year targeted to support the FID, according to the September announcement. In February 26, 2026, a release identified the underlying commitments as preliminary long-term agreements with TotalEnergies, JERA, Tokyo Gas, CPC, PTT and POSCO.

Key Contracts, Suppliers and Consultants
Worley (Phase 1 engineering and provisionally selected for engineering, procurement and construction management, subject to a definitive agreement); Corinth Pipeworks and Europipe (preliminary line-pipe supply agreements; and POSCO (steel); Baker Hughes (supply of LNG terminal main refrigerant compressors and gas treatment plant power generation equipment); Precision Pipeline; Price Gregory International; Michels Pipeline/Houston Contracting Company; Associated Pipe Line Contractors/Doyon Energy Services/Cruz Construction; Barnard Pipeline/SICIM; and Spiecapag/US Pipeline (conditional pipeline construction).

Contact Details for Project Information
AGDC, tel +1 907 330 6300. 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Airshrink - CiP
Airshrink - CiP

At Airshrink - CiP, we surpass customer expectations with innovative MV and LV cable accessories, including heat shrink joints, terminations,...

VISIT SHOWROOM 
Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 23 October 2026
Magazine round up | 23 October 2026
23rd October 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

➕

➕

➕

➕

➕

RESEARCH CHANNEL AFRICA

SUBSCRIBE

➕

➕

➕

➕

➕

➕

➕

➕

➕

➕

CORPORATE PACKAGES

CLICK FOR A QUOTATION

➕

➕







sq:0.067 0.207s - 158pq - 2rq
Subscribe Now