Third kiln commissioned at quicklime project

7th August 2026

     

Font size: - +

The hot commissioning of the third of eight planned kilns at its Limeco quicklime project in Zambia is under way, Africa-focused quicklime producer and critical minerals explorer Firering Strategic Minerals stated last month.

“The hot commissioning of Kiln 3 is a defining moment for Limeco. With all three kilns now in operation, we expect combined production to exceed 200 t/d, putting Limeco on track to becoming one of the largest high- quality lime producers in Zambia. Most importantly, this represents the inflection point for Limeco, moving from an effective breakeven operation into profitable production, with the business expected to be cash flow positive by year-end,” said Firering chairperson and interim CEO Youval Rasin.

He noted that the focus was to progress Kiln 3 to steady-state production and advance the renovation works on Kiln 4 in preparation for commissioning in a few months’ time.

He added that continued modifications to the hydration plant are expected to lift hydrated lime output beyond the current 100 t/d, while expressing delight that Firering has increased its interest in Limeco to 45%, further aligning it with the operation’s “long-term growth and value creation”.

In the operations update, the company noted that, following completion of the planned renovation of Kiln 3, the gasifier had been refired and Kilns 1 and 2 resumed production.

Kiln 3 was hot commissioned on July 20, with first quicklime production expected within a few days of the commissioning.

The company reported that modification works on Kiln 4 were ongoing and remained on track for commissioning by year-end.

“As additional kilns are brought online, Limeco will benefit from economies of scale, providing improved operating efficiencies [owing] to higher production outputs.”

Firering commented that Limeco’s lime is “recognised for its high purity and quality”, supporting demand from the mining, infrastructure, agriculture and industrial sectors.

As of mid-July, kiln feed had been sourced from existing surface stockpiles, which were nearly depleted. However, Limeco anticipated this, and started dewatering the existing quarry ensuring that the water levels dropped to below the previously blasted benches, providing easy access to more feed until such a time when a mining plan to widen and deepen the quarry is finalised.

Edited by Nadine James
Features Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

TSAM commemorates production of new Hilux
TSAM commemorates production of new Hilux
12th August 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.08 2.673s - 153pq - 2rq
Subscribe Now